Page 22 - State Law Summary of Mechanic's Lien Law
P. 22

Louisiana                                                                                               LA







        What is the statutory authority?
        LA. R.S. §§ 9:4801 - 9:4861, generally, and §§ 38:2242 and 38:2247.
        What is the Attachment Date of the Mechanic’s Lien?
        A mechanic’s lien attaches on the earlier of the date: 1) contractor records notice
        of contract; or 2) work or furnishing of materials commences that is visible by
        inspection. LA R.S. 9:4820 (A) (1) and (2).
        What constitutes visible commencement of construction?
        There is no visible commencement rule in Louisiana.
        What is the priority of the insured construction mortgage/
        deed of trust?
        A mortgage recorded before a notice of commencement has been filed or
        construction has commenced has priroity over mechanic’s liens. LA R.S. 9:4821(A)
        (2). A mortgage lender may rely on inspector’s affidavit (“No work affidavit”)
        stating that work has not commenced or materials placed if the mortgage is filed
        before or within 4 days of the affidavit being filed. LA R.S. 9:4820 (C).

        If priority of the insured mortgage/deed of trust is lost, is there a
        statutory procedure to regain priority?
        No.

        When does a mechanic’s lien have to be filed for claimant to maintain
        lien rights?
        A statement of claim must be filed no later than 60 days after the filing of a notice
        of termination of work or the substantial completion or abandonment of work if no
        notice of termination is filed. If a notice of contract is properly and timely filed, a
        subcontractor has no later than 30 days after the filing of a notice of termination of
        the work or 6 months after the substantial completion or abandonment of the work
        if no notice of termination is filed. A general contractor  must file its notice of claim
        no later than 60 days after the filing of the notice of termination and 7 months after
        the substantial completion or abandonment of the work if no notice of termination
        filed.  LA R.S. 9:4822(A)(B)(C).

        What is the period of enforcement of a filed mechanic’s lien?
        A lien claimant must act to enforce its lien against the owner within 1 year after
        filing a statement of claim according to LA .R.S. 9:4823(A)(2).

        Is there a procedure to bond over the mechanic’s lien(s)?
        Under LA R.S.9:4835, any interested person may deposit with recorder of
        mortgages either cash, certified funds or post a surety bond up to a total amount
        of 125% the principal amount to obtain a cancellation of a statement of claim or
        notice of pendency of action which the recorder will notate on the statement of
        claim or notice of pendency of an action.